Monday, August 9, 2010

9-8-2010

Damian rang me confirming tomorrows HO appointment we covered
1.All items on the internal list have been done
2.External items painter coming in to touch up front door,timber window.
3.gutters are being done today
4.Mortar is being cleaned

JOFI timber floorer starting on thursday to do the moisture barrier and the timber will come in on monday the 16th .He should finish by the 25th.

Wes meeting me on site to look at the driveway and start on Wed the 11th ,if no rain we are going with "maguire " from cranbourne mix exposed agge.

Fence lot 304 has not signed and sent in the return slip ,his waiting till his garage goes up and Lot 293 still has not sent in hers.Rang fencer said they will do another reminder again and I will on the 17th.

Monday, August 2, 2010

Construction manager to finish HO

Damian the construction manager rang me on the 2nd and the 3rd .He said he was finishing all the items on the list.
regarding the gaps on the timber windows he only fixed the large window and not the smaller ones
today the 3rd he said he rang me and said he will fix all the timber windows and caulk around the edges and not use quad.
I then rang him back again and asked him if all the items on the inside will be fixed .ClO rang back and said yes .
So HO is due on the 10th at 0800am

Friday, July 30, 2010

Handover was postponed on the 30th

At 1100 am SS who was resiging today rang me and said he the guys who were supposed to replace 1 of the sliding mirrors replaced the wrong one.
Damn that pissed me off ,he said everything was done including the external conduit .

I turned up shortly afterwards and most of the stuff on the outside was not completed such as mortar covering the timber windows,water in the gutters ,mortar not cleaned etc.
I made a written complaint to the CLO and requested the construction manager to get back to me as to why I was stuffed around.

I have the option of taking a letter of Undertaking but we that in my opinion is not a good option as these are important defects and incompete work ,Iam not waiting 3 months or running around after HO to get them fixed.

Tuesday, July 27, 2010

Monday, July 26, 2010

visited site 26-7-2010 apologise for the photo

I visited site and it seems work is progressing on getting all the items notated at PCI fixed.
I noticed on the outside they have removed the render that was covering the gap for the large timber window ,not the other smaller windows.
stickers were placed where the mortar needs cleaning and quads were used to cover other mortar imperfections in the alfresco.
It seems like the incorrectly cut bricks will be replaced.

Iam visiting the site this arvo to try and get a glimpse of the work on the inside.

I tried posting some photos ,seems like it didnt work I will try again tonight.

a few photos

http://img59.imageshack.us/img59/7708/p1000143k.jpg