The Painting finished on the 15-6-2010 and now its fixing of the cabinets ,cupboards etc
A FC sheet was installed to the front facade near the small windows instead of it being renderded. Have informed CLO and SS and waiting on outcome .
Was informed that PCI should be 15-7-2010 . Have got quotes for Driveway/Decking and paid deposit for Blinds and shutters .
Monday, June 21, 2010
Tuesday, June 8, 2010
8-6-2010
The Painter was on site about to start ,he said 7 days for painting . He wasnt sure where the feature went even though he had the sketches in front of him,pointed out feature to rumpus all 4 walls "tapestry beige ".
Brick infill stuff up not fixed ,emailed SS ,said he ordered lintet and it will be fixed next week, fibro cement piece near the small front window is to be painted not rendered ,I didnt like that ,might look odd. Emailed this to SS,lucky his approachable.
Casesarstone bench top installed for kitchen-"night sky" -they got that right.
Brick infill stuff up not fixed ,emailed SS ,said he ordered lintet and it will be fixed next week, fibro cement piece near the small front window is to be painted not rendered ,I didnt like that ,might look odd. Emailed this to SS,lucky his approachable.
Casesarstone bench top installed for kitchen-"night sky" -they got that right.
Thursday, June 3, 2010
4-6-2010
since the 17-5-2010 a lot has happened to the inside of the house
19-5-2010 Plaster installed
25-5-10 cornices installed
29-5-10 kitchen & cabinets in the ensuite & bathroom installed (wrong island laminate installed instead of tawny linewood /white was installed but it looks ok /larger so we took it.
28-5-10 -architraves & skirting installed
3-6-10 -underquote of render done and blinds & plantation shutters measured . We are installing a plantation shutter to the stacker door ,risk but looks good.
Parquetry installer also measured .installing sq/sq something different.
I was told the painter comes in next week and should take 7 days . tiler will take 3 days to the wet areas. Brick infill to be complete a BV not given to SS his not happy .
Iam guessing 2 months to PCI
19-5-2010 Plaster installed
25-5-10 cornices installed
29-5-10 kitchen & cabinets in the ensuite & bathroom installed (wrong island laminate installed instead of tawny linewood /white was installed but it looks ok /larger so we took it.
28-5-10 -architraves & skirting installed
3-6-10 -underquote of render done and blinds & plantation shutters measured . We are installing a plantation shutter to the stacker door ,risk but looks good.
Parquetry installer also measured .installing sq/sq something different.
I was told the painter comes in next week and should take 7 days . tiler will take 3 days to the wet areas. Brick infill to be complete a BV not given to SS his not happy .
Iam guessing 2 months to PCI