since the 17-5-2010 a lot has happened to the inside of the house 
19-5-2010 Plaster installed 
25-5-10 cornices installed 
29-5-10 kitchen & cabinets in the ensuite & bathroom installed (wrong island laminate installed instead of tawny linewood /white was installed but it looks ok /larger so we took it.
28-5-10 -architraves & skirting installed 
3-6-10 -underquote of render done and blinds & plantation shutters measured . We are installing a plantation shutter to the stacker door ,risk but looks good.
Parquetry installer also measured .installing sq/sq something different.
I was told the painter comes in next week and should take 7 days . tiler will take 3 days to the wet areas. Brick infill to be complete a BV not given to SS his not happy .
Iam guessing 2 months to PCI