Monday, August 9, 2010

9-8-2010

Damian rang me confirming tomorrows HO appointment we covered
1.All items on the internal list have been done
2.External items painter coming in to touch up front door,timber window.
3.gutters are being done today
4.Mortar is being cleaned

JOFI timber floorer starting on thursday to do the moisture barrier and the timber will come in on monday the 16th .He should finish by the 25th.

Wes meeting me on site to look at the driveway and start on Wed the 11th ,if no rain we are going with "maguire " from cranbourne mix exposed agge.

Fence lot 304 has not signed and sent in the return slip ,his waiting till his garage goes up and Lot 293 still has not sent in hers.Rang fencer said they will do another reminder again and I will on the 17th.

Monday, August 2, 2010

Construction manager to finish HO

Damian the construction manager rang me on the 2nd and the 3rd .He said he was finishing all the items on the list.
regarding the gaps on the timber windows he only fixed the large window and not the smaller ones
today the 3rd he said he rang me and said he will fix all the timber windows and caulk around the edges and not use quad.
I then rang him back again and asked him if all the items on the inside will be fixed .ClO rang back and said yes .
So HO is due on the 10th at 0800am